CentOS 7 Conversion Checklist
- Schedule host conversion
- Do disk prep
- Figure out disk space needed to preserve
- create dir on barge or freighter
- Run through Rich's document to get disk info and such
- copy any data
- update igor hosts file stanza for host
- build kickstart/preseed file for host on harbor
- make sure the host subnet is using package.ecn for pxeboot-server
- do final sync of data
- reboot host and start deploy
- finish the deploy once the deploy email hits the linux queue
- copy any data back
- notify folks host is ready to use again