  1. Schedule host conversion
  2. Do disk prep
    1. Figure out disk space needed to preserve
    2. create dir on barge or freighter
    3. Run through Rich's document to get disk info and such

  3. copy any data
  4. update igor hosts file stanza for host
  5. build kickstart/preseed file for host on harbor
  6. make sure the host subnet is using package.ecn for pxeboot-server
  7. do final sync of data
  8. reboot host and start deploy
  9. finish the deploy once the deploy email hits the linux queue
  10. copy any data back
  11. notify folks host is ready to use again