Abstract
The construction of temporary cofferdams is a
cyclic process that can expend a lot of resources. This paper will address the
construction of temporary box-type sheet pile cofferdams for the construction of bridge
piers. The construction of cofferdams requires the use of expensive resources that need to
be managed effectively. Through the use of a simulation program, we hope to address the
best management of resources for construction of temporary cofferdams.
Introduction
A cofferdam is a temporary construction method used in order to do
construction in wet excavations. The cofferdam is constructed in order to keep water out
of an excavation or work area with the aid of pumps. The cofferdam is a box like structure
fabricated through the use of a steel bracing system and steel sheet piles.
Heavy equipment is used in the construction of a cofferdam. Pile
drivers, cranes with clamshell buckets and concrete pumps trucks as well as pumps for
dewatering are used in the construction process. The effective management of equipment on
site as well as personnel is an important step in cost control and maintaining efficient
productivity.
Project Description
The project used for this study was the U.S. 231 concrete bridge
over the Wabash River on the southwest side of West Lafayette. The owner of the bridge is
the Indiana Department of Transportation. The contractor for the project was Rieth Riley
Construction Company. Construction began September 1993 and finished in August 1995. The
final cost was $20.5 million. The bridge consisted of a 12-span , 2100 foot, twin-roadway
bridge from abutment to abutment, with approaches to the abutments being part of a future
contract. The bridge is a reinforced concrete sub-structure and super-structure, with
pipe-pile group foundations. The super-structures consists of twenty-two piers; four of
which were built in the river via cofferdam construction.
The first phase in building the river piers is the construction of
a temporary bridge. The temporary bridge is needed for material handling and access to
river construction activities. The next procedure is to construct a template for the
cofferdam. The template serves two important measures. First, it is a guide for installing
the sheet piles for the cofferdam. The sheet piles must be driven perfectly plumb to
ensure the installation of the last pile. Second, the template provides all of the lateral
support needed during the dewatering process. The template is installed on falsework to
approximately the location of the desired cofferdam. The setting of the template takes
about a half a day. The falsework is usually installed in one day. The spuds (H-piles) are
driven through the cofferdam frame to provide an exact location and plumbness to the
frame. The frame is then slid up the spuds to the required elevation of the frame and the
falsework is then removed.
The next phase is to install sheet piles. The piles were started on
the up-river side of the cofferdam. This eliminated the problem of working against the
current during installation of the other three sides. The sheet piles should be driven
enough (not to grade) to keep the water current and the wind from affecting them. To
ensure a plumb cofferdam, every other sheet in the cofferdam is driven clockwise around
the cofferdam and then the remainder should be driven counterclockwise. This process helps
keep the cofferdam plumb during driving because the cofferdam slowly leans in the
direction of the driving.
After the sheet piles are in placed, excavation was begun inside
the cofferdam with a 1-1/2 cubic yard clam bucket. This process simply achieves the
desired elevation of the pier being constructed in the cofferdam. The excavation process
takes about a day and a half and another half day to clean it out with an
"air-lift". The air-lift, designed by Reith Riley Construction Company, works as
a vacuum and extracts the soil. It consist of installing an air hose from a compressor
inside a small diameter pipe to create this vacuum.
Pipe piles were used for the foundation. The pipe piles were driven
with a hydro-hammer S70 (70 Kip-feet), which is submersible if necessary. The crane then
positioned the pipe pile close to its pre-determined destination. The impact hammer clamp
on to it and drove it to its required depth. The piles are filled with concrete prior to
the placing of the tremie seal.
When placing the tremie seal, the first couple of yards (7 sack,
Class C mix, 2500 psi) were used to establish a cone on the bottom of the river. The pump
trucks discharge hose was submerged as far as possible without coming in contact
with the river bottom. The tremie seal is usually poured slightly low to insure that the
foundation may be formed correctly. Once the tremie seal has been placed and cured, the
contractor dewatered the cofferdam and cut the pipe piles to grade. The tremie seal was
cured for at least 3 days before dewatering.
The foundation for the pier was formed up. During this forming, the
cofferdam was continued to be dewatered. Once forming was complete, the foundation was
poured. The pier was then placed, the cofferdam was backfilled and filled back with water,
and then the sheet piles were pulled.
Description of Simulation Models
Several versions of the sheet pile, box cofferdam were developed
for simulation on Microcyclone. All the versions were done with construction of 100
cofferdams. No more than two cofferdams were simulated in construction at one time. The
following resources were considered in the models:
- Cranes: assisted in the falsework and template setting, setting and
driving sheet piles, excavation (w/bucket), and driving bearing piles (w/pile driving
rig).
- Crews: three main crews; falsework/template, piles, and concrete
crews.
- Concrete Pump: used for tremie seal and concrete for footer and
piles.
Duration Input
Durations were determined from video. Both measurements from the
construction process and from an interview with the project manager were used in
determining approximate duration for the activities. Two activities were simulated with a
small variance using a normal distribution: setting and driving sheet piles, and driving
the bearing piles. These activities contained the most unknowns due to soil conditions and
work process and had some variation in their durations due to these facts.
The duration of the dewatering activity was set at zero. The
cofferdams were assumed to be dewatered overnight, so that work could begin in the morning
on cutting the piles. It was also assumed that the work would be done in an eight hour
workday for ease of calculation.
Resource Costs
The costs of labor and equipment were considered for the simulation
of the sheet pile, box cofferdams. Indirect costs were not used in the simulation process.
For a complete project analysis, indirect costs should be portioned to the respective
activities of work and used in computation of savings for early completion. Because
indirect costs vary from company to company, they were not used. Material costs were also
not considered. The material costs do not change from simulation to simulation, so they
would not factor into cost decisions as to the method based on a simulation.
In Microcyclone, costs can either be fixed or variable costs.
Variable costs are only incurred when a resource is operating (such as, oil, fuel, etc.).
Fixed costs occur whether or not a resource is operating (such as, rental costs). The
equipment costs were split into variable and fixed costs. The fixed costs were based on
approximate rental costs for comparison study. The variable costs were assumed costs for
operation of the equipment. The crew costs were assumed to be variable costs. It was
assumed that when the crews were not working on the cofferdam, that they would be
reassigned to other parts of the project. The costs of labor were also assumed to be
$80/day/man; while this is low, it is easy to convert to local area wages to apply the
model. It should be noted that the costs were assumed on a daily basis (again, an eight
hour working day was assumed for analysis purposes).
Simulation Versions
For our simulation, six different versions were run on the
MicroCyclone program. Versions 1 through 3 used a crane to drive sheet piles, excavate and
drive bearing piles. Versions 4 through 6 used one crane to drive sheet piles and excavate
in addition to a separate crane used just for driving bearing piles (the activity for
attaching the pile rig was removed because it is not necessary for these three versions).
Due to site limitations, only one crane could excavate at a time (therefore only one
excavation bucket was used to alternate between cofferdams), and no more than two cranes
could be working at the same time. In all the versions only one concrete pump was used
because it is not a constraining resource for this simulation (a simulation was done
varying the concrete pump and productivity did not increase in any substantial amount).
Version 1
Version 1 used only one crane, one pile hammer, and one crew for
the setting and driving of all piles and any excavation. Refer to the table below for a
network summary for resources. Appendix A contains the network input, activity information
and process report.
|
Crew A |
Crew B |
Crew C |
Crane |
Pile Rig |
Avg. Wait (hrs) |
92.61 |
0.27 |
45.06 |
0.10 |
1.72 |
% Idle |
88.6% |
25.6% |
85% |
9.4% |
62.8% |
The total time to complete one cofferdam was 26.64
days at a cost of $26,387 per cofferdam. The crane was idle 9.4% of the time. The next
restrictive resource was Crew B (25.6% idle).
Version 2
Version 2 used two cranes and two crews with two pile hammers.
Refer to the table below for a network summary for resources. Appendix A contains the
network input, activity information and process report.
|
Crew A |
Crew B
(2) |
Crew C |
Crane (2) |
Pile Rig
(2) |
Avg. Wait (hrs) |
54.48 |
0.55 |
25.72 |
0.37 |
2.45 |
% Idle |
82.1% |
57.9% |
76.4% |
36.6% |
73.8% |
The total time to complete one cofferdam was 16.92
days at a cost of $32,133 per cofferdam. The crane was idle 36.6% of the time. The next
restrictive resource was Crew B, again (57.9% idle).
Version 3
Version 3 used two of every resource except the excavation bucket
for reasons mentioned earlier. Refer to the table below for a network summary for
resources. Appendix A contains the network input, activity information and process report.
|
Crew A
(2) |
Crew B
(2) |
Crew C
(2) |
Crane (2) |
Pile Rig
(2) |
Avg. Wait (hrs) |
119.56 |
0.55 |
59.04 |
0.37 |
2.45 |
% Idle |
99.8% |
57.8% |
100% |
36.4% |
73.8% |
The total time to complete one cofferdam was 16.91
days at a cost of $32,109 per cofferdam. The crane was idle 36.4% and Crew B was idle
57.8% of the time.
Version 4
Version 4 used one crane, one Crew B and one pile driving crane.
Refer to the table below for a network summary for resources. Appendix B contains the
network input, activity information and process report.
|
Crew A |
Crew B |
Crew C |
Crane |
Pile
Crane |
Avg. Wait (hrs) |
80.02 |
0.14 |
38.68 |
0.56 |
1.45 |
% Idle |
87.1% |
15.4% |
82.9% |
39.3% |
58.8% |
Total time to complete one cofferdam was 23.43 days
at a cost of $21,835. Crew B was the most restrictive resource with an idle time of only
15.4%. The crane was the next most critical resource with an idle time of 39.3%.
Version 5
Version 5 used two cranes, two Crew B and one pile driving crane.
Refer to the table below for a network summary for resources. Appendix B contains the
network input, activity information and process report.
|
Crew A |
Crew B
(2) |
Crew C |
Crane (2) |
Pile
Crane |
Avg. Wait (hrs) |
63.80 |
0.73 |
30.45 |
1.49 |
1.01 |
% Idle |
84.3% |
69.4% |
79.3% |
81.5% |
49.9% |
Total time to complete one cofferdam was 19.30 days
at a cost of $33,964. The pile crane was the most restrictive resource with an idle time
of 49.9%. Crew B was the next most critical resource with an idle time of 69.4%.
Version 6
Version 6 used two cranes, two Crew B and two pile driving cranes.
Refer to the table below for a network summary for resources. Appendix B contains the
network input, activity information and process report.
|
Crew A |
Crew B
(2) |
Crew C |
Crane (2) |
Pile
Crane (2) |
Avg. Wait (hrs) |
52.03 |
0.50 |
24.47 |
1.13 |
2.41 |
% Idle |
81.4% |
53.2% |
75.5% |
67.5% |
70.5% |
Total time to complete one cofferdam was 16.30 days
at a cost of $29,149. Crew B was the most critical resource with an idle time of 53.2%.
The next critical resource were the cranes at 67.5%. In comparison with the other methods,
version 6 is the preferred method, completing a cofferdam in the shortest amount of time
with a reasonable cost.
Summary and Conclusions
The following table shows a time-cost tradeoff between the
different versions.
Version
Comparison |
Duration (days per cofferdam) |
Cost ($/coffer) |
Change in
Cost (CC) |
Change in Duration (CD) |
CC/CD |
Best
Alternative |
Version
1 |
26.64 |
26,387 |
|
|
|
|
2
vs 1 |
16.92 |
32,133 |
+5,746 |
-9.72 |
591.16 |
2 |
3
vs 2 |
16.91 |
32,109 |
-24 |
-0.01 |
2403 |
3 |
4
vs 3 |
23.43 |
21,835 |
-10,273 |
+6.52 |
1575.6 |
4 |
5
vs 4 |
19.30 |
33,964 |
+12,129 |
-4.13 |
2,936.8 |
4 |
6
vs 4 |
16.30 |
29,149 |
-7,314 |
-7.14 |
1,024 |
6 |
To determine which version was a better alternative,
we used the following rules. If both CC and CD were positive, then
the new alternative is rejected. If both CC and CD are negative,
then the new alternative is accepted. If CC is positive and CD is
negative, accept the new alternative if the absolute value of CC/CD is less
than $1,000. If CC is negative and CD is positive, accept the new
alternative if the absolute value of CC/CD is greater than $1,000. The $1,000
is an assumed liquidated damage assessment on the project.
From the table above, version 6 is the best alternative for
construction. Version 6 consists of two cranes used for setting falsework, driving sheet
piles, and excavating; two crews (B); and two bearing pile driving cranes. While the crew
idle percentages are high for the cofferdam simulation, our assumption from the beginning
was that during idle periods the crews could be employed elsewhere on the project. For
example, the concrete crew (Crew C) could work in the prefabrication yard during idle
periods.
References
- Bureau of Reclamations. Design of Small Dams. 3rd
Edition. U. S. Government Printing Office, 1987. Pgs 493 to 502.
- Halpin, Daniel W. and Riggs, Leland S. Planning and Analysis of
Construction Operations. John Wiley & Sons, Inc. 1992.
- Havers, J. A. and Stubbs, F. W. Handbook of Heavy Construction.
2nd Edition. McGraw Hill Publishing, 1971. Pgs 28-3 to 30-25.
- Lee, D. H. Sheet Piling, Cofferdams, and Caissons. Concrete
Publications Limited, 1945.
- McCullouch, Bobby G. "Video: Rieth-Riley Constr. Co. Interview
& U.S. 231 Cofferdam", 1995.
- Naresh, Arcot L. and Jahren, Charles T. "Process Simulation for
Guide Wall Construction Using Mobile Cofferdams", Iowa State University.
- Tomlinson, M. J. Foundation Design & Construction. 6th
Edition. Longman Scientific & Technical, 1995. Pgs 414 to 455.
- White and Prentis. Cofferdams. 2nd Edition.
Columbia University Press, 1950.
|