Astrobotic Technologies Peregrine Lander
MMH/MON-25, 10 lbf attitude control enginesOctober 2021
April 2022
March 2023
Contract to TRR
Qualified 14 flight thrusters


Fig. 1. Actual assembly of the full Peregrine lunar lander (left) with some of the qualified flight thrusters (right). Courtesy of Astrobotic Technology, Inc.

Fig. 2. Theoretical illustration of Peregrine lunar lander on the moon. Courtesy of Astrobotic Technology, Inc.
Astrobotic Technologies Peregrine Lander
MMH/MON-25, 10 lbf attitude control enginesOctober 2021 - April 2022:
Contract to TRR
April 2022 - March 2023:
Qualified 14 flight thrusters


Fig. 1. Actual assembly of the full Peregrine lunar lander (left) with some of the qualified flight thrusters (right). Courtesy of Astrobotic Technology, Inc.

Fig. 2. Theoretical illustration of Peregrine lunar lander on the moon. Courtesy of Astrobotic Technology, Inc.