Dear Birck Users,

As part of the Birck Modernization Project the contractors need to begin working in N-Bay starting on Monday, Aug. 4 and continuing through that week, finishing their work late Friday, Aug. 8.  The entire bay will be shut down during this week-long period, and there will be no access to these tools during this time:


  *   Nanoimprint
  *   Hot Plates
  *   MJB3_2, MJB4, MA6, SB6, Heidelberg
  *   Spinner 1, Spinner 3
  *   Optical Microscopes
  *   Apreo SEM.

Please plan your research according to this schedule and this tool availability.