Dear Birck Users,

Wade Power Plant has lost two of four chillers so at this point chilled water to Birck is compromised.  Humidity control and equipment cooling water will be affected which could lead to future process issues and equipment cooling issues.  The physical facilities organization is aware and they're monitoring the situation.   Please be aware that if this condition is not corrected by tomorrow we will be forced to shut down air handling systems which will take equipment and processes offline.  (In order of priority, air handlers to the atriums and offices will be shed first in order to maintain temperature and humidity control in the labs and cleanroom.  If it progresses from there we will take the tour aisle down, keeping the cleanroom stable as long as possible.)

Our building personnel will continue to monitor this situation and keep us informed.

Ron

Ron Reger
Engineering Manager
Birck Nanotechnology Center | Room 2289 |
Office:  765.494.6667 | Email: rreger at purdue.edu<mailto:rreger at purdue.edu>
Wiki:  https://wiki.itap.purdue.edu/display/BNCWiki
iLabs:  https://purdue.ilabsolutions.com/homepage/

-------------- next part --------------
An HTML attachment was scrubbed...
URL: </ECN/mailman/archives/bnc-all/attachments/20220613/b69be074/attachment.htm>


More information about the BNC-all mailing list