[BNC-all] Possible Vibration at BNC
Weaver, John R
jrweaver at purdue.edu
Thu Apr 15 09:26:36 EDT 2010
Work is commencing on the enclosure for the Acid-Waste Neutralization (AWN) system. While the impact on any operations at BNC should be minimal, there will be some activities early in the project that could cause some vibration.
This activity will take place at the southwest corner of the BNC. This work will be done on concrete that is not connected to the BNC - any vibration would be transmitted through the ground. The closest vibration-sensitive equipment is the Vistec e-beam writer, about 35 feet away. Next would be the Titan TEM and the Raith e-beam, both about 175 feet away.
Weather permitting, the work will begin next Thursday, 22 April 2010, and last until the following Wednesday, 28 April 2010. Most of the activities will involve saw cutting, which should have no vibration impact. In some cases, however, a jackhammer will be used, and in all cases a backhoe and/or front loader will be used for the concrete removal. A more detailed schedule follows.
Work will take place from 7:30 AM to 4:30 PM weekdays. No work will take place on weekends.
Please contact Mark Voorhis if you experience any vibration-related issues.
Thank you for your understanding during this necessary construction effort.
Mark Voorhis John Weaver
Mark Voorhis John R. Weaver
Building Manager Facility Manager
Birck Nanotechnology Center Birck Nanotechnology Center
Purdue University Purdue University
(765) 494-3036 (765) 494-5494
mvoorhis at purdue.edu<mailto:mvoorhis at purdue.edu> jrweaver at purdue.edu
Date
Time
Vibration Activity
Thursday, April 22, 2010
7:30AM - 3:30PM
Saw cutting concrete
Friday, April 23, 2010
7:30AM - 3:30PM
Excavating cut concrete
Monday, April 26, 2010
7:30AM - 3:30PM
Excavating cut concrete & excavating dirt
Tuesday, April 27, 2010
7:30AM - 3:30PM
Excavating dirt & set forms, hammer drill existing concrete for rebar
Wednesday, April 28, 2010
7:30AM - 3:30PM
Pour & vibrate concrete
Future Work
Wednesday, May 26, 2010
7:30AM - 3:30PM
Crane operation to set building steel - using pneumatic impact wrenches
Thursday, May 27, 2010
7:30AM - 3:30PM
Crane operation to set building steel - using pneumatic impact wrenches
Friday, May 28, 2010
7:30AM - 3:30PM
Crane operation to set building steel - using pneumatic impact wrenches
Monday, May 31, 2010
7:30AM - 3:30PM
Crane operation to set building steel - using pneumatic impact wrenches
Tuesday, June 01, 2010
7:30AM - 3:30PM
Crane operation to set building steel - using pneumatic impact wrenches
-------------- next part --------------
An HTML attachment was scrubbed...
URL: </ECN/mailman/archives/bnc-all/attachments/20100415/520fecf5/attachment.html>
More information about the BNC-all
mailing list