Dear BNC Cleanroom and Ultra-Pure Water Users,

This is a reminder and an update for our scheduled power interruption for March 2, 2022 starting at 8AM.

Additionally the entire cleanroom space humidity control will be down due to the loss of ultrapure water required for cleanroom humidity control.  Any cleanroom research that requires tight cleanroom humidity control needs to pause and be protected during this interruption.   Below is the revised scope for the power interruption.

[cid:image002.png at 01D82949.D64D6F20]


Thank you,

Mark Voorhis
Building Manager
Purdue University
Birck Nanotechnology Center
Office: (765) 494-3036


From: Voorhis, Mark L.
Sent: Monday, February 21, 2022 8:19 AM
To: bnc-facility-notice at ecn.purdue.edu
Subject: RE: NOTICE - Ultra-Pure Water and Cleanroom Equipment Power Interruption

Dear BNC Cleanroom and Ultra-Pure Water Users,

The start time for the March 2 power interruption communicated below will start at 8:00AM on March 2, 2022 and lasting up to 8 hours based on no unforeseen issues.

Thank you,

Mark Voorhis
Building Manager
Purdue University
Birck Nanotechnology Center
Office: (765) 494-3036

From: Voorhis, Mark L.
Sent: Tuesday, January 25, 2022 4:40 PM
To: bnc-facility-notice at ecn.purdue.edu<mailto:bnc-facility-notice at ecn.purdue.edu>
Subject: NOTICE - Ultra-Pure Water and Cleanroom Equipment Power Interruption

Dear BNC Cleanroom and Ultra-Pure Water Users,

On March 2, 2022 starting at 9AM we are planning for a power interruption to add power for a major project in our bio cleanroom.  As a result we have to power down the northeast quadrant of the sub fab and cleanroom areas (image below).  The ultra-pure water system will have to be power down resulting in a shutdown of all UPW water for all labs and cleanroom areas.

At this time we are planning that the power outage with the ultra-pure water recovery time could last 24 hours, but we hoping that this time can be shorten when more information becomes available as we approach March 2, 2022.

Please let me know if you have any questions or concerns.

Best Regards,

Mark Voorhis
Building Manager
Purdue University
Birck Nanotechnology Center
Office: (765) 494-3036


[cid:image001.png at 01D82947.EC46A820]









-------------- next part --------------
An HTML attachment was scrubbed...
URL: </ECN/mailman/archives/bnc-facility-notice/attachments/20220224/9ff87387/attachment-0001.htm>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.png
Type: image/png
Size: 210275 bytes
Desc: image001.png
URL: </ECN/mailman/archives/bnc-facility-notice/attachments/20220224/9ff87387/attachment-0002.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image002.png
Type: image/png
Size: 201484 bytes
Desc: image002.png
URL: </ECN/mailman/archives/bnc-facility-notice/attachments/20220224/9ff87387/attachment-0003.png>


More information about the Bnc-facility-notice mailing list