Please see the attached shutdown schedule for the east wing of the BNC.

Note the second crane lift (details in attached PowerPoint) and the revised laboratory shutdown dates. 

Also, note the shutdown of all hoods in the east wing beginning next Monday, 17 December 2012. All hoods in the east wing of the Birck Nanotechnology Center will be shut down at 7:00 am Monday morning, 17 December 2012. All hazardous materials - chemical and biological - must be removed from the hoods prior to that time. We hope to have the hoods operational by the end of the day on Friday, 21 December 2012. Please watch for a bnc-facility-notice e-mail and the removal of the signs before using a hood in the east wing.

Hoods in the west wing of the facility will NOT be affected by this work.

Thank you for your patience during this critical project.

John

John R. Weaver
Facility Manager
Birck Nanotechnology Center
Purdue University
(765) 494-5494
jrweaver at purdue.edu


-------------- next part --------------
A non-text attachment was scrubbed...
Name: Shutdown Schedule 10Dec12.xlsx
Type: application/vnd.openxmlformats-officedocument.spreadsheetml.sheet
Size: 16272 bytes
Desc: Shutdown Schedule 10Dec12.xlsx
URL: </ECN/mailman/archives/bnc-facility-notice/attachments/20121210/950666a8/attachment-0001.bin>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: Crane Lift Shutdown Plan Fans.pdf
Type: application/pdf
Size: 463993 bytes
Desc: Crane Lift Shutdown Plan Fans.pdf
URL: </ECN/mailman/archives/bnc-facility-notice/attachments/20121210/950666a8/attachment-0001.pdf>


More information about the Bnc-facility-notice mailing list