[BNC-all] Cleanroom shutdown and update

Dave Lubelski lubelski at purdue.edu
Fri Aug 4 09:42:53 EDT 2006


The Birck cleanroom will be down for maintanence on Thursday and part of
Friday of next week 8/10-8/11.  Please do not enter the cleanroom during
this time.  If you have chemicals in any hood in the cleanroom, please
make sure they are all taken care of by midnight on the 9th.  Anything
left after that point will be disposed of as waste.
The Triode etcher may be up and running by the end of next week.  Casey
is working dilligently to try and get this system up by 8/11/06
The (Si) DRIE blower had to be sent back for repair again.  It is
expected to be gone about two weeks.  I will update all users when the
system is online.

Dave Lubelski


More information about the BNC-all mailing list